IMP-007 · Implementation
Issue UAT readiness notice
Notify the client that the configured milestone is ready and start the agreed UAT review period.
High
Due 10 Aug 2026, 12:00 AM
Contractual Requirement and Action Plan
BIZ-2026-00002
Taxmanntri Consultancy Private Limited
Taxmanntri Consultancy Private Limited
Acceptance
Bizzomation Software
info@finwellgrowth.com
Finwell
info@finwellgrowth.com
Finwell
10 Aug 2026, 12:00 AM
Not Sent
Not uploaded
Internal Action Points
Provide UAT access, test cases, readiness evidence and deadline.
Evidence Required
Readiness notice and delivery proof.
Prepared Client Communication
Not SentUpload Compliance Evidence
Update Control Record
Why This Is a Risk
Due in 41 day(s)Risk classification considers contractual severity, current status and time remaining. Red items require immediate action and evidence-based closure.
29 Jun 2026, 05:55 PM
—
None
once
Complete Activity Trail
No activity recorded.